Drills outside the 'red' building: Kypseli residents halt metro works and take their case to the mayor
Athens' Metro Line 4 tunnel boring machine has been stuck under Kypseli since May, and the buildings above it are cracked. Now digging has started at a building rated unsafe – without a finished structural study, residents say. They are distrustful, anxious and increasingly angry.
What happened
The tunnel boring machine for Athens' new Metro Line 4 has been stationary beneath the densely built district of Kypseli since May 2026. Buildings above it have subsided and cracked; one building on Spetson Street has long been rated 'red', meaning unsafe. Completion of the line has already been pushed back from 2029 to 2032.
On 5 November, crews from the construction consortium led by AVAX and the state company Elliniko Metro began work right in front of that building: exposing columns and beams, taking soil samples, drilling and delivering bags of cement and sand. The consortium calls this inspection and preparatory ground reinforcement in line with instructions from the Technical Chamber of Greece (TEE), which is initially checking five buildings above the machine. Residents see it as preparation for restarting the boring machine.
On 11 November about 15 residents stood in front of the drilling rig, and work was halted until the consortium replies in writing to their lawyer. On Friday, representatives of the residents' initiative met Athens Mayor Haris Doukas at City Hall. No restart date has been set; according to the consortium, the machine will only resume once the checks have been assessed and residents informed.
The mood on the ground
Distrust dominates in Kypseli. According to Efsyn, six months after the problems began there is still neither a structural study nor a support plan for the affected building – and people keep living in it without shoring. They fear for their homes and feel the consortium mainly wants to get the project moving again.
Flash.gr describes the scene at the rig: residents say they 'put their bodies in front' because letters and questions went unanswered. They report irritated engineers and calls to the police, who were supposed to check the permits and never came. Trust, their statement says, cannot be rebuilt with zero information.
The other side is relaxed: people close to the project told Efsyn that 'a non-existent issue' had been created and that the works serve to secure the foundations. According to Ethnos, the consortium stresses that repair crews are on standby. The initiative sets three conditions before the machine may bore again: full repair of damaged homes, structural and geotechnical checks of all affected buildings, and open, public studies on the restart.
Voices from the media
Sources
This article was rewritten from local-language sources. Every statement about the mood is based on the linked reports.
How this article was made
This article was researched, translated and written in our own words with the help of artificial intelligence, based on the local sources listed above. The assessment of the public mood is based solely on these reports. Learn more →
Share this story
For Instagram: on your phone, tap «Share …» and choose Instagram (story or message).
Follow Weltpuls on InstagramThe world mood and the day's strongest stories – right in your feed.@weltpuls ↗