Cracks in Kypseli, metal fences in Exarchia: Athens' new metro line leaves whole neighbourhoods anxious

The tunnel boring machine of metro Line 4 has been idle beneath Kypseli since May, houses have cracks and no restart date has been set. Now Athens' mayor is demanding guarantees and temporary housing – while residents keep wondering whether their homes are safe.

Weltpuls newsroom · · 2 min read
Mood in the countryUncertainty
Concern Divided

What happened

Line 4 is the largest public transport project in Athens. From March 2026, ground settlement beneath the densely built Kypseli district was greater than calculated, and cracks appeared in apartment buildings. On 8 May the tunnel boring machine was stopped as a precaution – it has not moved since.

According to a press conference held by the ministry and the construction consortium in mid-October, 87 buildings are being monitored individually; damage was found in 20 of them, mostly non-structural cracks. No assessment by the Technical Chamber has declared a building unfit for use, and the consortium is paying for repairs. Before any restart, the ground ahead of the machine is to be reinforced; no date has been set.

In an interview with Efsyn on Saturday, Mayor Haris Doukas painted a bleaker picture: settlement was up to four times greater than predicted, and one building is still classed as at risk after a third inspection. The city is demanding that affected families be temporarily rehoused with all housing costs covered. In Exarchia, a court ordered the worksite on the square to be fenced off, and old trees near Rizari Park were at risk. The line is officially due in 2032; according to Doukas, 2034 or 2035 is now being discussed.

The mood on the ground

In Kypseli, people have lived for months not knowing whether their flats are safe. As early as September, Proto Thema reported that a residents' representative had called for urgent support work on several buildings; there was talk of families moving out for ten to fifteen days while the machine passes beneath their homes.

Residents stress that they are not against the metro – but they want firm commitments before drilling resumes. Members of the residents' initiative attended the October press conference; the ministry and consortium promised to inform them before every step.

In Exarchia, residents won in court but, according to Doukas, still live behind metal sheeting with little progress. Who is to blame is disputed: in the reader comments on Efsyn, some accuse the mayor of grandstanding, others blame the consortium and the constant delays.

Voices from the media

Efsyn · AthensLeft-leaning Efsyn gives the mayor room to argue that neither safety risks nor costs may be shifted onto residents.
Oikonomikos Tachydromos (OT) · AthensBusiness paper OT presents the view of the ministry and consortium: the damage is mostly superficial and the monitoring worked.
Proto Thema · AthensProto Thema describes a marked loss of residents' trust in the project's safety.

Sources

This article was rewritten from local-language sources. Every statement about the mood is based on the linked reports.

How this article was made

This article was researched, translated and written in our own words with the help of artificial intelligence, based on the local sources listed above. The assessment of the public mood is based solely on these reports. Learn more →

Spotted a mistake? Let us know: redaktion@weltpuls.ch

Share this story

WhatsApp Facebook X LinkedIn Email

For Instagram: on your phone, tap «Share …» and choose Instagram (story or message).

Follow Weltpuls on InstagramThe world mood and the day's strongest stories – right in your feed.@weltpuls ↗

More stories from Athens

From TVinvestment.ch

Business articles on Greece
All articles on Greece at TVinvestment.ch →